Macedon Battery Energy Storage System

About The Project

The proposed Macedon BESS Project is a 100 MW 4-hour Battery Energy Storage System (BESS) that enhances grid stability by providing a bi-directional energy function, helping to smooth out fluctuations and allowing an increased supply of cost-effective clean renewable energy. The Macedon BESS project is expected to charge and discharge stored energy enough to power the equivalent of approximately 35,000 households for a 4-hour discharge cycle.

Spanning across approximately 5 hectares of land, the Macedon BESS Project will be located approximately 3.5 km south of Macedon township, and about 60 km north-west of Melbourne, Victoria state’s capital.

The project is currently under development with construction expected to commence in early 2027, achieving full operation in Q2 2028.

Project Status

Location
Macedon,VIC

Installed Capacity
100MW/400MWh

Network Operator
Powercor

Feasibility Assessment
In Progress

Development Approval
In Progress

Connection Approval
In progress

Power Purchase Agreement
To be updated

Financial Close
Early 2027

Construction Date
Early 2027

Operation Date
Q2 2028

PROJECT SITE