Goorambat Solar Farm

About The Project

Goorambat is a rural township 17 km north of Benalla on the way to Yarrawonga. The Goorambat Solar Farm will be located 430 metres south-east of the Goorambat township in country Victoria. Situated on approximately 130 hectares of farm land, it is well-positioned to receive excellent exposure to northern Victoria’s rich solar resource.

South Energy initiated the development of Goorambat Solar Farm back in 2019 and formed a partnership with Lightsource BP in 2021 to jointly deliver the project. Financial close has been set to be achieved by Q4 2024, and commercial operation date by Q4 2026.

Project Status

Location
Goorambat, VIC

Installed Capacity
86 MWdc

Generation Capacity
75 MWac

Network Operator
AEMO

Feasibility Assessment
Completed

Development Approval
Granted

Connection Approval
In Progress

Financial Close
Q4 2024

Construction Date
Q1 2025

Operation Date
Q4 2026

Project Partner

Project Site