Frasers Solar Farm
About The Project
Frasers Solar Farm is located about 5 km north of Glengarry, a small town within the Latrobe Valley, Victoria. Covering nearly 110 hectares, the solar farm is well positioned to provide clean energy in response to the retirement of conventional power plants in the region.
Frasers Solar Farm is currently undergoing early works with the preferred EPC contractor. The grid connection process has been completed and approval was granted in June 2022. Financial close and EPC notice to proceed are expected in Q4 2026, with construction planned to commence in Q1 2027. Commercial operations are targeted for Q3 2028.