Campbells Forest Solar Farm

About The Project

The Campbells Forest Solar Farm is located approximately 20 km northwest of Bendigo on Pyramid-Yarraberb Road in Loddon Shire, Victoria. Covering around 360 hectares of cleared rural land, the project is well placed to provide clean energy to the growing township of Bendigo.

The project is currently under bidding review for a Power Purchase Agreement (PPA) with potential off-takers. Generator Performance Standards (GPS) have been approved by AEMO, and connection contracts are scheduled for execution in Q4 2025. EPC contractor engagement is underway, with financial close also targeted for Q4 2025. Construction is planned to commence in Q1 2026, with commercial operations expected by Q4 2027.

Project Status

Location
Campbells Forest, VIC

Installed Capacity
233 MWdc

Generation Capacity
205 MWac

Network Operator
AEMO

Feasibility Assessment
Completed

Development Approval
Granted

Connection Approval
GPS approved | Contract under review

Power Purchase Agreement
Under discussion with interested parties

Financial Close
Q4 2025

Construction Date
Q1 2026

Operation Date
Q4 2027